15 Oct Alstom Transport France – Constantine Tramway, Algeria (2011): Engineering and Design of the “Traction Power Substations” Automation System
Posted at 09:00h
in news
ES PROCESSING performed the study, design, engineering and commissioning of the entire system including Automation PLC/HMI, Emergency tripping system, Interlock/Intertrip system, Calculation sheets…
The project consisted of designing, engineering and commissioning of the automation system of the traction power substations of Constantine Transit System. The Constantine Transit System consists of 6 substations (including “Depot”). The system was designed to ensure the control of all traction power substations of Constantine network.
The automation substations are equipped with PLCs (Schneider Premium) and Remote rack I/O (STB) on each board.