Alstom Transport France – Singapore CCL Subway (2010): Engineering and design of Traction Power Substations of the Automation System

The project consisted of engineering, designing, and commissioning of the “traction power substations” automation system. The Singapore Circle Line (CCL) has 32 traction power substations. The system ensures control over all traction power substations of the Singapore network.

The automation per sub-station consisted of the PLC (Siemens S7-300 type) and Remote rack I/O (ET200S).